Project Scope:
The project will generally consist of pavement milling, miscellaneous sidewalk and curb and gutter repair, new asphalt pavement, culvert removal and replacement, ditch grading, and landscape restoration. During the course of construction, your grass adjacent to the concrete improvements may be damaged. The Contractor will restore the damaged areas once all the work has been completed.
Typical to projects of this nature, residents may experience the following during construction:
• Construction traffic and noise
• Minor traffic delays
• Temporary driveway closures
Through construction management, it is the City’s intention to minimize these impacts when feasible. The City will communicate directly with residents regarding temporary driveway closures prior to occurrence. Additionally, the City will coordinate and notify residents of any changes to garbage and/or mail service.
Project Schedule:
April 7, 2025 - May 30, 2025
Contractor:
D Construction
Project Contact Information:
Name: Christian Correa
Title: On-Site Resident Engineer
Company: Engineering Enterprises, Inc.
Phone Number: 630-201-7933