Eldamain Water Loop- South

Project Scope:

This project is located along Faxon Rd from Alan Dale Ln to Beecher Rd, Beecher Rd from Faxon Rd to BNSF Railroad, BNSF Railroad from Beecher Rd to Faxon Rd, Faxon Rd from BNSF Railroad to Eldamain Rd, Eldamain Rd from Faxon Rd to 850 feet south of Corneils Rd.

The water main  project involves the installation of approximately 1,400 feet of 12-inch and 11,500 feet of 16-inch ductile iron water main.

The project will involve the installation of new water mains and fire hydrants. The new main will be tested before connected to the existing water system and the roadway will be patched and landscaped areas restored with seed and fertilizer.  Farm fields will be restored with 12" of topsoil and chisel plowed and ditches, parkways, and other grassed areas will be restored to their original shape, contour, and condition.

During construction, there may be temporary disruptions to  traffic and access to properties. 

Story Map Outlining Project

Project Schedule:

March 2025 - June 2025

Contractor:

Winninger Excavating, Inc.

Project Contact Information:

Name: Todd Wells 

Title: Project Manager 

Company: Engineering Enterprises, Inc.

Email: twells@eeiweb.com

Phone Number: 630-466-6758