2025 Road Program - II

Project Scope:

This resurfacing project is located on various streets south of Kennedy Rd between McHugh Rd and Hayden Dr, Waterpark Way, Beecher Rd south of Rt 34 and concrete patching on E Countryside Pkwy from McHugh Rd to Rt 34, and McHugh Rd from E Countryside Pkwy to Rt 34. 

This maintenance project consists of pavement patching, pavement milling, pavement resurfacing, curb and gutter removal and replacement, sidewalk removal and replacement, driveway removal and replacement, structure adjustments, restoration, crack sealing, pavement markings, and all other work necessary to complete the project. The mill and overlay involves removing the top layer of existing pavement (milling) and then applying the new layer of asphalt (overlay) to the road surface. 

The project will involve milling the existing pavement to a specified depth, typically around 2 to 4 inches. Patching may also be performed at areas of failing pavement. It is advised to avoid driving your vehicle on your driveway until the tack coat has set up; typically after a few hours. This process helps to restore the structural integrity of the road, improve driving conditions, and extend the life of the pavement.

New asphalt may be driven on as soon as the rolling process has been completed.  Please note that the new asphalt is very hot, and residents and especially pets should avoid walking on the new surface for several hours.                                                                                                                                                                                                                                                                                                               Concrete patching will be completed on E Countryside Parkway and McHugh Rd. Lane closures and traffic detours will be used.                                                                                                                         

During construction, there may be temporary disruptions to water service, traffic, parking and access to properties. 

Story Map Outlining Project

Project Schedule:

July 2025 - October 2025

Contractor:

TBD

Project Contact Information:

Name: Chris Ott

Title: Project Manager

Company: Engineering Enterprises, Inc.

Email: cott@eeiweb.com

Phone Number: 630-466-6757