Case Number: 2025-07
Notice:
The Project Steel development will be presented at an upcoming public hearing during the Tuesday, June 24th City Council meeting at 7:00PM to review the proposed Annexation Agreement.
Originally, the project was scheduled to appear before the Economic Development Committee (EDC) on June 3rd, but that meeting was canceled due to a lack of quorum. It was subsequently rescheduled for the July 1st EDC meeting, with a public hearing before the Planning and Zoning Commission (PZC) set for Wednesday, July 9th to consider requests for rezoning, special use / Planned Unit Development (PUD), and a preliminary PUD plan.
However, the developer has since requested to revise the schedule. Project Steel will now appear for informal plan feedback at the Tuesday, August 5, 2025 EDC meeting at 6:00PM, and a formal public hearing will be held at the Wednesday, August 13, 2025 PZC meeting at 7:00PM for review of the rezoning, special use / PUD, and preliminary PUD plan requests.
Because no public hearing notices were published and no mailings were sent to nearby property owners for the previously scheduled July 9th PZC meeting, the August 13th meeting will serve as the official public hearing.
The developer will be present at the June 24th City Council, August 5th EDC, and August 13th PZC meetings to provide an overview of the project and respond to questions from both the public and City officials
Proposed Project
Prologis, L.P., as the petitioner and contract purchaser, along with property owners Rosenwinkel Family Trust, George Ostreko Jr. Et Al, Mary Auer, and Jerry G. Marilee Foltz, have submitted applications to the United City of Yorkville, Kendall County, Illinois, requesting annexation, annexation agreement, rezoning, special use authorization for a Planned Unit Development (PUD), and preliminary PUD Plan approval for approximately 540 acres across sixteen (16) parcels. The proposal aims to rezone the parcels from R-1 Single-Family Suburban Residence District to M-2 General Manufacturing District to facilitate the development of a high-tech data center campus, which will include eighteen (18) data center buildings totaling over 9 million square feet, three (3) electrical substations, and associated stormwater detention basins. Requested deviations from the Yorkville Unified Development Ordinance (UDO) include modifications to interior yard setbacks, energy use standards, minimum parking requirements, cross access, pedestrian circulation, bicycle parking, off-street loading spaces, landscaping, mechanical unit screening, fencing, industrial appearance standards, frontage on public streets, and public street and circulation requirements. The subject property is generally located east of Eldamain Road between Corneils Road on the south and Galena Road on the north.
Proposed Location
Documents
- Application for Annexation
- Application for Preliminary PUD Plan
- Application for Planned Unit Development
- Application for Rezoning
- Surrounding Property Owners within 500'
- Owner Authorizations
- Legal Description Consolidated Parcel A
- Revised Legal Description Consolidated Parcel A
- Legal Description Consolidated Parcel B
- Project Steel Narrative
- Preliminary PUD Plan
- Landscape Plan
- Phasing Plan
- Rendering 1
- Rendering 2
- Traffic Memo
- Updated Preliminary PUD Plan dated 5-16-25
- Updated Conceptual Landscape Plan dated 5-16-25
- Applicant Response Letter dated 5-16-25
- Security Fence Detail
- Petitioner's Presentation 6-24-25
- Petitioner Follow-up Responses to City Council Public Hearing 6-24-25
- Updated Preliminary PUD Plan submitted 7-25-25
- Updated Conceptual Landscape Plan submitted 7-25-25
- Updated Building Elevations submitted 7-25-25
- Updated Building Rendering submitted 7-25-25
- Petitioner's Presentation 8-5-25
- Updated Landscape Plan submitted 8-7-25
- Preliminary Sound Study Report
- Petitioner's Presentation for Planning & Zoning Commission Public Hearing 8-13-25
Public Meeting Schedule
The following meeting schedule for this project is tentative, and subject to change:
Economic Development Committee (EDC)
| Tuesday, June 3, 2025 at 6PM The Economic Development Committee meeting scheduled for June 3, 2025 at 6:00 PM has been CANCELLED due to lack of quorum. This project is now scheduled for Tuesday, August 5, 2025 at 6PM |
City Council Public Hearing - Annexation Agreement Only
| Tuesday, June 24, 2025 at 7PM It is anticipated that the City Council will hold the public hearing on the annexation agreement only - although the decision to open, close, and/or continue the public hearing will be made by the City Council at the meeting. |
Planning and Zoning Commission (PZC) - Public Hearing
| Wednesday, August 13, 2025 at 7PM |
City Council | Tuesday, August 26, 2025 at 7PM |
Public Hearing Notices
CITY COUNCIL
The public hearing for annexation agreement is scheduled for Tuesday, June 24, 2025 at 7:00 PM at the United City of Yorkville, City Hall, located at 651 Prairie Pointe Drive, Yorkville, Illinois 60560. Remote attendance will also be available via Zoom. All interested parties are invited to attend the public hearing and will be given opportunity to be heard. Any written comments should be addressed to the United City of Yorkville Community Development Department, City Hall, 651 Prairie Pointe Drive, Yorkville Illinois, and will be accepted up to the date of the public hearing.
PLANNING & ZONING COMMISSION
The public hearing for rezoning, special use authorization for a Planned Unit Development (PUD), and preliminary PUD Plan approval is tentatively scheduled for Wednesday, August 13, 2025 at 7:00 PM at the United City of Yorkville, City Hall, located at 651 Prairie Pointe Drive, Yorkville, Illinois 60560. Remote attendance will also be available via Zoom. All interested parties are invited to attend the public hearing and will be given opportunity to be heard. Any written comments should be addressed to the United City of Yorkville Community Development Department, City Hall, 651 Prairie Pointe Drive, Yorkville Illinois, and will be accepted up to the date of the public hearing.
Additional Information
For further information, contact the Community Development Director, Krysti Barksdale-Noble, at knoble@yorkville.il.us or 630-553-8573.
Contact Us
-
Krysti Barksdale-Noble
Community Development Director
Email
Phone: 630-553-8573David Hansen
Senior Planner
Email
Phone: 630-553-8588Sara Mendez
Senior Planner
Email
Phone: 630-553-8555City Hall
651 Prairie Pointe Drive
Yorkville, IL 60560
Phone: 630-553-4350
Fax: 630-553-7575Hours
Monday - Friday
8 a.m. - 4:30 p.m.