Countryside Water Main and Road Improvements









Concrete work and pavement binder course installation is expected to be completed within Phase 2 of the project by October 21st, barring weather delays. Topsoil placement and seeding within Phase 1 and Phase 2 of the project should also be completed by October 21st. Water main installation within Phase 3 is scheduled to begin soon and is to be completed by mid-November. The concrete work, pavement binder course, topsoil placement and seeding in Phase 3 should be completed by the end of November.

The project will involve the replacement of over 15,000 feet of 8 and 12 inch water main and the resurfacing of the streets within the Countryside subdivision.
The project is expected to start in mid-April and continue through November of this year. It is anticipated that all of the water main work and the installation of the binder course pavement will be completed this year. The final lift of asphalt (surface course) is expected to be installed in the spring of 2017.

Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.

Mid-April 2016

Summer 2017

United City of Yorkville

$4,900,000 (Construction Only)

Typical to projects of this nature, residents may experience the following during construction:
  • Brief periods of water service loss and discolored water
  • Construction noise and traffic
  • Minor traffic delays
  • Limited tree removal
  • Temporary driveway closures
  • Temporary relocation of mailbox
Kyle Welte, P.E - Resident Engineer (EEI)

Construction Notice
Driveway Apron and Curb Replacement Program
Full Project Map