Construction

2017 Road to Better Roads (RTBR)


This project will consist of the milling and resurfacing of the pavement along several streets within the City as noted in the attached map. The project may begin as early as May and should be completed by late-September. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected. 

2017 Sanitary Sewer Lining


This project will involve the installation of cured-in-place pipeliner in existing sanitary sewer in several locations within the City as shown on the attached map. This project may begin as early as June and should be completed by November. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.

Center Pkwy and Countryside Pkwy Resurfacing


This project utilizes City funding and will consist of the milling and resurfacing of the pavement along Center Parkway and Countryside Parkway from Route 34 to Route 47 as shown on the attached map. The project may begin as early as May and should be completed by early-August. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.

Countryside Water Main and Road Improvements


This project that began last year involves the replacement of over 15,000 feet of 8 and 12 inch water main and the resurfacing of the streets within the Countryside subdivision as shown on the attached map. At this time all major water main work and installation of the binder course pavement has been completed. Project work has resumed and will wrap up by summer of 2017. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.

Kennedy Road Resurfacing


This project utilizes City and County funds and will consists of the resurfacing of the pavement along Kennedy Road from the Autumn Creek Subdivision to Galena Road as shown on the attached map. Patching may begin as early as May with paving and remaining work to be completed by early-September. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.

Kennedy Road Shared-Use Path - ITEP


This project utilizes Federal funds and will consist of the installation of a 8-10 foot wide shared-use path along Kennedy Road from Illinois Route 47 to Bridge Park as shown on the attached map. The project is scheduled to be begin in July and should be completed by the end of November. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected. 

Route 34 Improvements


This IDOT project consists of the reconstruction of US Route 34 from Route 47 to Orchard Road in Oswego. The project began in January 2016 and is anticipated to be complete by December 2018. Significant traffic delays are expected.

West Washington Street Water Main Replacement


Update: Project will be starting the week of May 8
This project involves the installation of 8 inch water main along West Washington Street from Main Street to Morgan Street as shown on the attached map. This project is anticipated to be underway in May and should be completed by the end of June. Impacts to traffic are expected to be minimal; however daytime lane and roadway closures should be expected.